GROSVENOR INQUIRY KEY ISSUE 5 SUBMISSION. INRUSH DEFINITION CHANGE and NEW SPECIFIC ‘METHANE INRUSH STANDARD OPERATING PROCEDURE” REGULATION
Below is my Submission for a Change to the Definition of Inrush and for a New specific “Methane Inrush Standard Operating Procedure” Regulation.
KEY ISSUE 5 SUBMISSION INRUSH DEFINITION CHANGE
Att 1 Brown Direcrive floor heave gas Grosvenor Coal Mine – 04.05.2017
Att 2 Grosvenor LW104 Methane HPI Table Floor versus Goaf
The Submission is 6 pages all up and the start reads
FINDING 1
There has been an incorrect terminology applied by both the Grosvenor Mine and the Mines Inspectorate since the first Methane Inrush in Development in 2016.
They have used the term “Floor Heave” and then regularly state as ‘being accompanied by’ or ‘associated with’ an uncontrolled methane “release”.
Methane is a “gas”.
RECOMMENDATION 1
The CMSHR 2001 Definition of “Inrush” in Schedule 9 be amended to
“inrush means an unplanned or uncontrolled flood “or release” of liquid, gas or material that has the potential to create a hazard.”
RECOMMENDATION 2
Creating a new specific “Methane Inrush Standard Operating Procedure” Regulation