5th September Grosvenor Electrical MRE

  • September 9, 2020

POINTS TO NOTE Shift Tradesman Reports scanned and emailed to engineering and maintenance staff as well as EEM and MEM. No sign off of reports, what evidence they are read…

22nd August 2016 Fall MG 101 21-22 ct MRE GROSVENOR

  • September 9, 2020

POINTS TO NOTE Reported to duty Inspector Graham Callinan (Rocky area?) on weekend. No time of report indicated. Over 1 hour since the Management were aware, I would guess. Inspector…

5th July 2016 Roof Fall GROSVENOR LW 101 Maingate

  • September 8, 2020

05.07.2016 Fall MG 101 Face + comments MRE - Grosvenor Coal Mine - POINTS TO NOTE Roof Fall occurred at 9:30pm on 4/07/2016 and Inspectors informed at 1:01am 5/07/2016. 07/07/2016…

1st April 2016 LW 101 Second Workings Meeting

  • September 8, 2020

POINTS TO NOTE The intent of the meeting was to establish an open forum for discussion on Grosvenor Longwall 101 Second Workings. A presentation was given by representatives of the…