1st April 2016 LW 101 Second Workings Meeting
POINTS TO NOTE
The intent of the meeting was to establish an open forum for discussion on Grosvenor Longwall 101 Second Workings. A presentation was given by representatives of the Senior Management Team
GAS MANAGEMENT PRESENTATION BASED ON PLAN EXISTS AS AT 1ST APRIL 2016
GCM STRATA STUDY SHOULD EXIST
DUST MANAGEMENT PLAN SHOULD EXIST THAT ADDRESSES THESE POINTS AS A MINIMUM
Use of TOLK product for strata consolidation, due diligence required on checking the material and consideration to health monitoring if used.
PUR USE PROCESS
Goaf wells planned to be used and management thereof.
WHAT WAS THE PRESENTED PLAN?
In regards to TARPs, the Mines Management Structure needs to reflect the positions within the TARPs in line with recent changes of structure at the Mine.
FIRST INDICATION OF FREQUENT ROLE CHANGES AND NEW MANAGEMENT PERSONELL
At the close out of the meeting, UMM Mr Wayne Bull presented Inspectors for perusal, the
Risk Assessment for Second workings, Version 1 GRO-6898-RA LWIOI Secondary
Workings, dated 12 January 2016 and, Draft SOP Version 2 Second workings LWIOI .
WAS IN THE INSPECTOR FEEDBACK?
WHEN WAS IT SENT?
WHAT WAS THE PROCESS FROM THEN ON?
01.04.2016 MRE and Comments – Grosvenor Coal Mine – 101 2nd work