Grosvenor 29 LW Methane HPI’s in 2019 and 14 in 2020 before the Ignition on May 6th. What happened to May 2018 “It was also acknowledged that continued HPI’s with Methane greater than 2.5% was not satisfactory and the mine must ensure that such HPl’s are minimised, and preferably eliminated going forward.”? SWEET F… ALL!

  • July 30, 2021

It was also acknowledged that continued HPI’s with Methane greater than 2.5% was not satisfactory and the mine must ensure that such HPI’s are minimised, and preferably eliminated going forward.…

The meeting was called at the request of Inspector Marlborough to discuss the recent 27 exceedances of 2.5% methane in the LW102 TG. Reconsidering if the bleeder could be made a return. Inspector Marlborough requested a copy of the Ventsim model which was the basis for the Mine decision to discount this option

  • July 19, 2021

A further 22 Methane HPI's occur between the 18th of January and the 19th of March 2018. On Monday 19 March 2018, Inspectors Marlborough, Brown and Gouldstone held a meeting…