North Goonyella Mine Fire 23rd September 2018. “TB29 H2 Jumped To 550 And Then 745ppm — Higher CO & Hydrocarbons Followed. TB38 (Eframe) & TB14 (MG Chute) Are Now Beginning To Show Presence Of Heating Products”

North Goonyella Mine Fire 23rd September 2018. “TB29 H2 jumped to 550 and then 745ppm — higher CO & hydrocarbons followed. TB38 (Eframe) & TB14 (MG chute) are now beginning to show presence of heating products”

MRE – North Goonyella – 23.09.2018.pdf

The Situation at North Goonyella is now getting worse daily.

It was reiterated by Inspector Gouldstone that it is the Mine’s decision on how best to effect the plan but to ensure acceptable level of risk to those who may be affected.

Discussion

  1. Gas analysis was discussed and from 5:45 am results came through that showed that –

TB29 H2 jumped to 550 and then 745ppm — higher CO & hydrocarbons followed

too o TB28 reflected the same

TB38 (Eframe) & TB14 (MG chute) are now beginning to show presence of heating products – analysis records requested by G. Nugent(lnspector of Mines) by email separate to the meeting which Mr Stook undertook to provide e Mine understood that bag sampling would be necessary since +1000ppm CO level had been reached

Interpretation of the sudden increases was, that the anticipated flushing effect caused by introduction of liquid nitrogen to hole 2698, or, it could be acceleration of the spontaneous combustion event. The meeting was advised that the associated ratio information did not support accelerated oxidation.

  1. Nitrogen injection had been decreased as liquid nitrogen supply to 2698 ran out at 1 1 pm last night — refiguration of the nitrogen feed will be considered at 1M T to target as much to GN2698 as possible (more liquid Nitrogen due 4pm today)
  • Plan B ie plug TG chute will take 18 hours to effect so work will continue to give this option while gas trends are continually reviewed. It was reiterated by Inspector Gouldstone that it is the Mine’s decision on how best to effect the plan but to ensure acceptable level of risk to those who may be affected.
  1. The Mine undertook to continue to keep inspectors informed of how matters progress.

Inspector Richard Gouldstone arrived at NGC Mine at 07:15am on Sunday 23 September 2018 to attend a meeting in regard to progress on dealing with the spontaneous combustion event currently in progress. Meeting at 8:30am Sunday 23 September 2018

Attendees –

Peter Purdie (in attendance in the absence of SSHRs)

Richard Gouldstone (Inspector of Mines)

Jeff Perks (Superintendent Health Safety &Training)

John Anger (SSE)

Steven Stook (Tech Services Manager)

Dennis Black (VO)

John Martin (Development Coordinator)

Lee Earnshaw (Development Coordinator)

By dial in Sean Dobson (Deputy Chief Inspector) for briefing session but not the extended meeting including the other call — ins, which were as follows –

Michael Brady (Consultant) Darren Brady (Consultant), Neville Impson (Compliance

Manager), Marek Romanski (UMM), Martin Watkinson (SIMTARS), Mike Carter (SSE

Millennium)

Mr Anger explained

Last 24

Drilling GN2700 – depth at EOS NS at 170m

Drilling GN2698 completed well at 22:30 and relocate to GN2696 re-drill

Set up over GN2696 and recover inside casing — 282m of casing pulled out by EOS

NS

Drilling GN2699 on DS to 222m, set / pressure grout casing and wait for grout to cure

Relocated Rig 1227 from GN2696 to standby location

3rd Narrabri unit ETA on site Tuesday next week

Liquid N2 flow reduction by 1411/s over the duration of NS

Liquid N2 re-tasked from GN2693 to GN2698 at 23:00pm

Overall decrease of 1 001/s from start of shift DS 22/9/18

Floxal 6 capacity split to enable GN2693 injection at 105 1/s and retained capacity into GN1991 at 249 Ms at 22:30pm

RE-ENTRY PLAN : RA – chute road sealing (to allow underground entry to extract LW9N supports) – review plan

Cattle grid underpass for tube bundle run cleaned out and tube bundle run out from hut to Main Floxal area entry point

Test run on the surface, running hoses and clamping around rods for GN2697 to understand timing of activity to sync in with completion of GN2700 hole through and tube bundle installation used an available borehole in GM South Re-calibrate the tube bundle

Next 24

QMRS Foam prepare set up for GN2700 hole through

RE-ENTRY PLAN RA – chute road sealing (to allow underground entry to extract LW9N supports) – review WRAC

RA – review Wilsons remote sealing, identified identical hazards and will require re-ranking using Peabody matrix

Drilling GN2699 – drill out cement shoe and drill to target depth

Drilling GN2700 – drill out to target depth (2nd hole for tube bundle monitoring in tailgate chute rd.)

Re-drilling GN2696 after pulling out of inside casing and re-establish inside casing Bag sample from GN2696

Continue filling in Mine Re-entry Assessment System (MRAS) questionnaire , 5 modules completed

Take Bag samples from TB#14 and TB#38 shiftly

Liquid N2 ran out at 0632am, re-tasking GN2695 Floxal capacity to GN2698

Other Items

Tuesday 25th September – Floxal maintenance planned

Identify compatibility of Millennium Floxal compressors with Narrabri AFTECH unit (Floxal 6)

Optimise volume distribution for re-entry plan – taking into consideration latest TB28 trends and consider re-tasking capacity from MG side

Discussion

  1. Gas analysis was discussed and from 5:45 am results came through that showed that –

TB29 H2 jumped to 550 and then 745ppm — higher CO & hydrocarbons followed

too o TB28 reflected the same

TB38 (Eframe) & TB14 (MG chute) are now beginning to show presence of heating products – analysis records requested by G. Nugent(lnspector of Mines) by email separate to the meeting which Mr Stook undertook to provide e Mine understood that bag sampling would be necessary since +1000ppm CO level had been reached

Interpretation of the sudden increases was, that the anticipated flushing effect caused by introduction of liquid nitrogen to hole 2698, or, it could be acceleration of the spontaneous combustion event. The meeting was advised that the associated ratio information did not support accelerated oxidation.

  1. Nitrogen injection had been decreased as liquid nitrogen supply to 2698 ran out at 1 1 pm last night — refiguration of the nitrogen feed will be considered at 1M T to target as much to GN2698 as possible (more liquid Nitrogen due 4pm today)
  • Plan B ie plug TG chute will take 18 hours to effect so work will continue to give this option while gas trends are continually reviewed. It was reiterated by Inspector Gouldstone that it is the Mine’s decision on how best to effect the plan but to ensure acceptable level of risk to those who may be affected.
  1. The Mine undertook to continue to keep inspectors informed of how matters progress.